Installation updates
These are the current fiber installation projects in our area and the most recent information we have about what’s happening with them.
— Last updated 9/7/2023
-
Most of this project area is in the final installation phase. Rolling Ridge, Hwy 60 in Spring Green, and Rainbow Rd. are in an earlier phase. See https://ruclightspeed.com/sg3/ for more information.
-
Note: A portion of the Town of Arena will have Lightspeed as a provider and a portion will have MHTC. If you are not sure what portion you are in, please provide your address and we can let you know! (broadband@rivervalleycommons.org / 608-588-7428)
The Town of Arena portion of the project is in the project design and engineering phase (Phase 1). The Town of Wyoming portion is in the design & engineering phase (Phase 2). Enrollment is still open for this project. Construction is expected to begin in late Fall 2023. See https://ruclightspeed.com/iowa-county-project/ for more information.
-
The Town of Troy in included in Lightspeed’s Witwen project.
A portion of the project is in the project design and engineering phase (Phase 1). The other portion is in the design & engineering phase (Phase 2). Enrollment is still open for this project. Construction is expected to begin in late Fall 2023. See http://ruclightspeed.com/witwen-project/or more information.
-
Note: A portion of the Town of Arena will have Lightspeed as a provider and a portion will have MHTC. If you are not sure what portion you are in, please provide your address and we can let you know! (broadband@rivervalleycommons.org / 608-588-7428)
Arena is part of MHTC’s “Rural Barneveld North” project, which is divided into two phases.
Phase 1 is underway and has been divided into 4 work areas. Arena roads are divided as follows:
Phase 1, area #2: Southern portion of HH, western portion of Sweeney Rd, southern portion of K, Pinnacle Rd, Spring Rd.
Phase 1, area #4: Roberts Rd, most of Blue Ridge Rd, Knutson Rd.
The rest of the Town of Arena is included in Phase 2.
Currently…
Phase 1, area #2 is in the construction phase, with 10% completed.
Phase 1, area #4 has not yet started.
Phase 2 has not yet started.
For more information, see https://mhtc.net/fiber-process/
-
The Town of Buena Vista is included in Lightspeed’s Bear Valley/130 project.
This project is in the engineering phase (Phase 1). Enrollment is still open. Construction is expected to begin in early Fall 2023. See https://ruclightspeed.com/bear-valley-130/ for more information.